Thursday, Aug. 16, 2018

Innovative field joint coating solution

Written By:

|

07/02/2018

|

Posted In:

February 2018 Contact us
Innovative field joint coating solution

Onshore line pipe operations involve welding pipes together to form a pipeline. The field joint coating covers the gap where two coated line pipe sections meet and are welded together, in other words: “where there’s a weld, there’s field joint coating”. Serimax Field Joint Coating (FJC) has developed an innovative and revolutionary solution – OrbiterTM which has been tried and tested in the field.

Manual coating application in the field has been the typical process for coating welded pipe joints. Often the client is anxious that field joint coating will cause a delay to the project, slowing down the welding operations and they demand faster solutions with greater process traceability and lower costs. Time is of the essence in welding operations and the field joint has to be implemented as fast as possible for the laying rate to be optimal. In the field, project execution requires significant coordination between both the welding and coating contractors, to avoid bottlenecks and prevent any slowdown. The industry has been waiting for a solution that would work well across the full range of pipe diameters, with reduced manning while delivering high quality performance.
Serimax Field Joint Coating took up the challenge.

 

Light, fast, automated, revolutionary

Adopting the field proven Serimax bug and band technology, the Serimax FJC design team, led by Andrew Stribley, Engineering Manager, designed Orbiter™, a two-component liquid coating system. The technology not only reduced capital costs, but also importantly resulted in faster process speeds, reduced manning and lower solvent usage. Orbiter™ is a robust, light-weight, automated spray machine with process monitoring and data recording. Shunning the use of mechanized lifting equipment, it makes for a fast and safe option for coating landline field joints with multi-component liquid systems. Its speed, reliability, ergonomics and efficiency make it revolutionary in the small world of FJC.

Proof is in the field

Theory is one thing, but it’s out in the field, in real life, you see the quality of field equipment. Prior to its release to market, the machines were extensively tested, using Serimax FJC technologists and operators before being demonstrated to respected industry consultants. OrbiterTM has since proven its worth on 250 km of pipeline, running from the Caspian Sea through Azerbaijan and Georgia to Turkey.
Serimax’s OrbiterTM first real life challenge was in Georgia, Caucasus. The environment was as tough as it gets: difficult access and arduous terrain, wet and snowy conditions as well as strong winds. In addition to the unfavorable time of year, the teams only had a very short period to mobilize equipment and materials in the country, with a meager 4 weeks’ notice. Beating the odds, over 4,000 field joints were completed on schedule, including nearly 1,500 ­tie-in joints.
Serimax FJC is currently working to close out the Azeri section, having coated over 20,000 field joints with a very low repair rate. The Azeri section allowed for a daily average of 120+ joints per day, in summer conditions, and 70 joints per day, in winter conditions, where post-heat was added to speed up the curing of the material.

 

Meeting and exceeding customer expectation

The new coating technology has ensured a significant reduction in personnel required on a project. For example, on high throughput main-line coating of 48-inch pipes with liquid epoxy systems, it’s possible to halve the head count. Removing the reliance on vehicles with mechanical lifting systems, makes it easier and cheaper to supply equipment in many regions of the world where access would have been a major headache. Furthermore, in terms of speed, with the innovative OrbiterTM system, it is now possible to outpace any welding crew, without significant change to the equipment profile. It’s just a matter of balancing the manning level to the target output and number of vehicles used.

 

Organization and Project Management

Andrew Mullins, Project Manager tells: “The delivery of a project starts in Blackburn (UK), where we pack and check every item required from disposable gloves and screwdrivers through to containerised coating units for project use. The next step is sourcing and training local labor to assist with the project. Once on site we then set the equipment up,  perform job safety analysis  and start the work. Our supervisors perform daily site reports to keep our management team in the loop.” Managing projects and logistics overseas can be as challenging as the in-field operations, due to restrictions on importing; manning and team work with language barriers and local ethics or beliefs. Running projects smoothly with diplomacy, understanding and efficiency is just as essential. Serimax has the experience and know-how to handle the most complex aspects of project management surrounding Field Joint Coating, as it has with welding services, for many years.

Share This Article

News

Global Solutions for the Sole <br> offshore gas project in Australia
Shaped Pipes: custom made  <br> for every one  of your projects
Making our tubes “Intelligent” <br> thanks to Open Innovation

About Author

vallourec